Metering Skid Fabrication: How a Skid Is Engineered, Built and Tested

Technology 8 min read

A metering skid is a pre-fabricated, pressure-tested assembly of meter runs, instruments and a flow computer mounted on one frame. Two metering skids can look identical on a drawing and behave very differently on site. The difference is rarely the meter; it is the work around it: layout, welding and inspection, instrument checks and the evidence handed over at the end. This article walks through that work stage by stage. For skid types and applications, see our metering skids overview; here the focus is how a skid is made and how to judge its maker.

1. Process data and the P&ID

Fabrication starts long before steel is cut. The design basis fixes fluid and composition, minimum, normal and maximum flow, operating and design pressure and temperature, line sizes, pressure class, hazardous area classification and the purpose of measurement: process monitoring, allocation or custody transfer. Gaps here become rework later. Our guide on what process data an RMS/PRMS quotation needs lists the typical items for gas stations.

From that basis the P&ID is drawn: number of meter runs and redundancy, filtration, isolation and double block-and-bleed points, pressure relief, sampling or gas quality connections, prover or master meter connections for liquid service, and every instrument with its tag.

2. Meter selection and the measurement chain

Meter technology follows the fluid and the duty: orifice, ultrasonic or turbine for gas; Coriolis, positive displacement, turbine or ultrasonic for liquids. The meter is only one link in a chain with pressure and temperature transmitters, density or composition data and a flow computer. The calculation standard is fixed here too, for example ISO 5167 or AGA Report No. 3 for orifice gas metering, API MPMS chapters for liquid hydrocarbons, because it dictates tapping points, straight lengths and flow computer configuration. Why a flow computer rather than a PLC carries the billing calculation is explained in this comparison.

3. 3D layout, straight run and flow conditioning

The 3D model is where measurement quality is protected or lost. Upstream elbows, reducers and valves distort the velocity profile and create swirl, so each meter needs the straight lengths or flow conditioner arrangement required by its standard and manufacturer. The layout must also allow plate withdrawal, transmitter access, valve operation, lifting and the shipping envelope. A useful review question: can every instrument be removed and every valve operated without dismantling pipework?

On orifice skids, the meter tube and plate holder are treated as one dimensionally controlled assembly, because system accuracy depends on both, as described on our orifice gas metering skids page.

4. Materials and welding: WPS, PQR and NDT

Pipe, fittings and flanges are bought to the material specification, mill certificates are checked against the material received, and traceability runs from heat number to spool.

Welding follows qualified Welding Procedure Specifications (WPS), each supported by a Procedure Qualification Record (PQR), and is done by welders qualified for that procedure. Welder qualification records (e.g. ISO 9606-1 or ASME IX WPQ) are the usual evidence of this. Non-destructive testing (visual, radiographic or ultrasonic, magnetic particle or dye penetrant) is applied to the extent required by the design code, for example ASME B31.3 for process piping, and by the project specification. Results are recorded on a weld map so each joint can be traced to its welder, procedure and inspection report.

5. Skid frame, surface preparation and painting

The structural frame carries the piping, instruments and cabinets, and must survive lifting, transport and site loads. Surface preparation and the coating system are defined by the project specification and the environment; ISO 12944 is a common reference for corrosivity categories. Dry film thickness and adhesion checks are recorded.

6. Pressure and leak testing

The welded assembly is pressure tested, usually hydrostatically, at the test pressure and hold time set by the design code and the specification. Instruments that could be damaged are isolated or removed, and the skid is drained and dried afterwards. A leak test of the final assembly with instruments installed typically follows.

7. Instrument integration and loop checks

Transmitters, temperature elements, meters and the flow computer are mounted, tubed and wired with hazardous-area-rated equipment. Each loop is checked from field device to flow computer: tag, range, units, signal and alarm. Instrument calibration certificates are collected for the data book.

8. Factory acceptance test with the flow computer

The FAT shows the buyer, before shipment, that the skid matches the approved drawings and behaves as specified. It typically covers dimensional and visual inspection, document review, loop tests and a functional test of the flow computer: configuration, calculations against simulated inputs, alarms, audit trail and communication with the plant PLC or SCADA. Agree the procedure in advance, and close every punch item or formally carry it to site.

9. Data book, shipping and site commissioning

The data book (manufacturing record book) collects the evidence produced at each stage: material certificates, WPS/PQR and welder qualifications, NDT reports, pressure test records, coating reports, calibration certificates, signed FAT report and as-built drawings. The stage summary below shows where each document comes from. The skid is then preserved, packed and shipped. On site, after installation and tie-in, commissioning repeats the critical checks under real process conditions and hands the system over to operations.

Stage summary

  • Design basis and P&ID — What is checked: Process data, redundancy, instrument list; Document produced: Design basis, P&ID, instrument index

  • Meter and standard selection — What is checked: Meter type, sizing, calculation standard; Document produced: Sizing calculations, datasheets

  • 3D layout — What is checked: Straight run, flow conditioning, access, lifting; Document produced: GA drawings, isometrics

  • Materials and welding — What is checked: Material grades, WPS/PQR, welder qualification, NDT; Document produced: Mill certificates, weld map, NDT reports

  • Frame and painting — What is checked: Structure, surface prep, coating thickness; Document produced: Coating inspection report

  • Pressure test — What is checked: Strength and tightness at code test pressure; Document produced: Pressure test record

  • Instrument integration — What is checked: Wiring, tagging, loop function; Document produced: Loop check sheets, calibration certificates

  • FAT — What is checked: Function, flow computer configuration, alarms, SCADA link; Document produced: Signed FAT report, punch list

  • Shipping and commissioning — What is checked: Preservation, installation, live operation; Document produced: Data book, commissioning report

Frequently asked questions

What is the difference between a FAT and site commissioning? The FAT proves the skid in the factory against drawings and simulated signals. Commissioning proves it in the plant, with real process conditions and the site control system.

Is the flow computer tested during the FAT? It should be. Configuration, calculations with simulated inputs, alarms, event logs and communication can all be checked before shipment, which shortens commissioning.

Why do WPS and PQR matter to a buyer? They show that the welding procedure was qualified by test before production welds were made. Without them, weld quality depends on individual skill rather than a controlled process.

Can straight run be shortened to fit a small skid? Sometimes, using a flow conditioner arrangement accepted by the meter standard and manufacturer. It must be decided at layout stage, not on the shop floor.

What should be in a metering skid data book? Material certificates, welding and NDT records, pressure test records, coating and calibration reports, the FAT report and as-built drawings, as listed in the order.

Buyer checklist: choosing a metering skid manufacturer

  • Does the supplier fabricate in its own workshop, and which items are made in-house versus bought in?

  • Can it show a welding quality certificate (such as EN ISO 3834) and qualified WPS/PQRs for your materials?

  • Who performs NDT, and to what extent is it specified?

  • Is straight run and flow conditioning shown on the 3D model and checked against the meter standard?

  • Is the FAT procedure, including flow computer tests, agreed before fabrication ends?

  • Is the data book content listed in the purchase order?

  • Who is responsible for site commissioning, and is support available afterwards?

How TLY Energy builds metering skids

TLY Energy designs metering skids from the process data up and fabricates them in its own workshop in Türkiye, with welding carried out under an EN ISO 3834-2 certified quality system and a TÜRKAK-accredited ISO 9001:2015 quality management system. Skid frames, process piping, filter housings, heaters, orifice fittings and meter runs are TLY-made; meters, transmitters and flow computers are selected for the application and integrated, including products of the brands we represent, such as EPS Leading and Ex~i Flow Measurement. After fabrication, pressure and leak tests and a FAT are carried out; depending on scope we also provide site installation, PLC or SCADA integration, commissioning and after-sales support, as with our gas pressure reduction and metering stations. More about the company is on our About Us page.

Request a quote

Send your process data, P&ID or specification to our engineering team and we will review layout, testing scope and documentation with you. Contact TLY Energy.

Share this post

Have questions?